Runs in your browser
Solvent extraction plant
Enter the seed the plant crushes and how much oil is in it. The list below is what that implies — preparation, extractor, desolventiser-toaster, distillation and solvent recovery — with a rate column you fill in yourself.
Your figures
Seed or cake into the plant, not oil out of it.
Extraction plants run continuously — stopping one is expensive.
Soya about 18%, rapeseed cake 12%, rice bran 16%. Sets the oil side of the plant.
Hexane circulating against seed. Sets the extractor, the distillation and the pumps.
Drives the hexane storage and the vent recovery. Under 1.5 is a well-run plant.
Crude oil and miscella are usually mild steel here; stainless is a specification choice.
Material take-off
What to buy, at what size, and how many — worked out from the figures above.
Every line is estimated from those two figures: its steel — or steel-equivalent — mass at the steel rate, stainless at 3.2×, plus its install days at the labour rate. There is no price feed behind this, so the two anchors are seeded from typical Pakistan figures as of September 2026 and are yours to correct. Type over any individual rate and yours is used instead.
Seed preparation
| Material | Size | No. | Total weight | Rate | Amount |
|---|---|---|---|---|---|
| Seed cleaner with magnetic separatorStones and tramp metal out before the rollsRate from 2,983 kg + 3 days labour — Screen deck, aspiration and magnet | 8,333 kg/h | 1unit | — | estimated | 1,200,833 |
| Cracking rollsSeed broken to four to six pieces before flakingRate from 5,967 kg + 4 days labour — Chilled rolls, frame and drive | 8,333 kg/h | 2unit | — | estimated | 4,793,334 |
| Conditioner / cooker, steam heatedBrings the seed to flaking temperature and moistureRate from 7,200 kg + 5 days labour — Stacked heated trays with agitators | 8,333 kg/h | 1unit | — | estimated | 2,892,500 |
| Flaking millFlakes to about 0.3 mm — the thinner the flake, the better the extractionRate from 10,700 kg + 5 days labour — Heavy rolls, hydraulic loading and drive | 8,333 kg/h | 2mill | — | estimated | 8,585,000 |
| Expander / extruderCollets drain faster and hold less solvent than raw flakeRate from 12,967 kg + 6 days labour — Barrel, screw, drive and steam injection | 8,333 kg/h | 1unit | — | estimated | 5,201,667 |
Seed cleaner with magnetic separator
Stones and tramp metal out before the rolls
Rate from 2,983 kg + 3 days labour — Screen deck, aspiration and magnet- Size
- 8,333 kg/h
- No.
- 1unit
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 1,200,833
Cracking rolls
Seed broken to four to six pieces before flaking
Rate from 5,967 kg + 4 days labour — Chilled rolls, frame and drive- Size
- 8,333 kg/h
- No.
- 2unit
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 4,793,334
Conditioner / cooker, steam heated
Brings the seed to flaking temperature and moisture
Rate from 7,200 kg + 5 days labour — Stacked heated trays with agitators- Size
- 8,333 kg/h
- No.
- 1unit
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 2,892,500
Flaking mill
Flakes to about 0.3 mm — the thinner the flake, the better the extraction
Rate from 10,700 kg + 5 days labour — Heavy rolls, hydraulic loading and drive- Size
- 8,333 kg/h
- No.
- 2mill
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 8,585,000
Expander / extruder
Collets drain faster and hold less solvent than raw flake
Rate from 12,967 kg + 6 days labour — Barrel, screw, drive and steam injection- Size
- 8,333 kg/h
- No.
- 1unit
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 5,201,667
Extraction
| Material | Size | No. | Total weight | Rate | Amount |
|---|---|---|---|---|---|
| Solvent extractor, continuousHexane at 1.1 : 1 against seedRate from 46,500 kg + 25 days labour — Loop or belt extractor, gas-tight, with drives and hoppers | 200 t/day31.0 t eachsite-erected | 1extractor | 31.0t | estimated | 18,662,500 |
| Miscella tank, MSTwo hours of miscella, full and half strengthRate from 3,724 kg + 4 days labour — Gas-tight tank with vent connection | 40 m³3.1 t each | 2tank | 6.2t | estimated | 2,998,914 |
| Miscella filterFines out of the miscella before distillationRate from 1,205 kg + 3 days labour — Leaf filter, gas-tight | 18.2 m² | 2filter | — | estimated | 979,120 |
| Hexane storage tank, MSA week of make-up at 1.2 kg/t plus working inventoryRate from 5,286 kg + 6 days labour — Bunded tank with flame arrestor and nitrogen blanket | 60 m³4.1 t each | 2tank | 8.1t | estimated | 4,258,772 |
Solvent extractor, continuous
Hexane at 1.1 : 1 against seed
Rate from 46,500 kg + 25 days labour — Loop or belt extractor, gas-tight, with drives and hoppers- Size
- 200 t/day · 31.0 t eachsite-erected
- No.
- 1extractor
- Total weight
- 31.0 t
- Rate(estimated)
- Amount
- ₨ 18,662,500
Miscella tank, MS
Two hours of miscella, full and half strength
Rate from 3,724 kg + 4 days labour — Gas-tight tank with vent connection- Size
- 40 m³ · 3.1 t each
- No.
- 2tank
- Total weight
- 6.2 t
- Rate(estimated)
- Amount
- ₨ 2,998,914
Miscella filter
Fines out of the miscella before distillation
Rate from 1,205 kg + 3 days labour — Leaf filter, gas-tight- Size
- 18.2 m²
- No.
- 2filter
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 979,120
Hexane storage tank, MS
A week of make-up at 1.2 kg/t plus working inventory
Rate from 5,286 kg + 6 days labour — Bunded tank with flame arrestor and nitrogen blanket- Size
- 60 m³ · 4.1 t each
- No.
- 2tank
- Total weight
- 8.1 t
- Rate(estimated)
- Amount
- ₨ 4,258,772
Desolventising
| Material | Size | No. | Total weight | Rate | Amount |
|---|---|---|---|---|---|
| Desolventiser-toaster (DT)Strips hexane from the meal and cooks it to specRate from 28,867 kg + 20 days labour — Stacked heated trays, sparge, drive and vapour hood | 6,833 kg/h meal20.0 t eachsite-erected | 1unit | 20.0t | estimated | 11,596,667 |
| Meal dryer and coolerMeal to storage moisture and ambient temperatureRate from 14,133 kg + 8 days labour — Dryer-cooler with fans and cyclones | 6,833 kg/h | 1unit | — | estimated | 5,673,333 |
| Meal conveying, grinding and baggingOut of the cooler and into the silo or the bagRate from 9,917 kg + 8 days labour — Redler, elevator, hammer mill and bagger | 6,833 kg/h | 1line | — | estimated | 3,986,667 |
| Meal silo, MS5 days of meal at 600 kg/m³Rate from 37,352 kg + 8 days labour — Silo with hopper bottom, ladder and level | 1400 m³27.7 t eachsite-erected | 2silo | 55.3t | estimated | 29,921,878 |
Desolventiser-toaster (DT)
Strips hexane from the meal and cooks it to spec
Rate from 28,867 kg + 20 days labour — Stacked heated trays, sparge, drive and vapour hood- Size
- 6,833 kg/h meal · 20.0 t eachsite-erected
- No.
- 1unit
- Total weight
- 20.0 t
- Rate(estimated)
- Amount
- ₨ 11,596,667
Meal dryer and cooler
Meal to storage moisture and ambient temperature
Rate from 14,133 kg + 8 days labour — Dryer-cooler with fans and cyclones- Size
- 6,833 kg/h
- No.
- 1unit
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 5,673,333
Meal conveying, grinding and bagging
Out of the cooler and into the silo or the bag
Rate from 9,917 kg + 8 days labour — Redler, elevator, hammer mill and bagger- Size
- 6,833 kg/h
- No.
- 1line
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 3,986,667
Meal silo, MS
5 days of meal at 600 kg/m³
Rate from 37,352 kg + 8 days labour — Silo with hopper bottom, ladder and level- Size
- 1400 m³ · 27.7 t eachsite-erected
- No.
- 2silo
- Total weight
- 55.3 t
- Rate(estimated)
- Amount
- ₨ 29,921,878
Distillation & solvent recovery
| Material | Size | No. | Total weight | Rate | Amount |
|---|---|---|---|---|---|
| Rising-film evaporator, MSTwo stages take the miscella from about 25% to 90% oilRate from 12,935 kg + 6 days labour — Tube bundle, shell and separator, per m² | 136.2 m²12.9 t each | 2stage | 25.9t | estimated | 10,378,060 |
| Final stripping column, MSSteam strips the last hexane out of the oilRate from 2,929 kg + 8 days labour — Packed or disc-and-doughnut column with sparge | 1.65 m³/h oil2.1 t each | 1column | 2.1t | estimated | 1,191,692 |
| Solvent condensersCondense the hexane vapour from DT, evaporators and stripperRate from 25,208 kg + 4 days labour — Shell and tube condenser, per m² | 296.6 m² | 3unit | — | estimated | 30,279,999 |
| Solvent-water separator and boiling tankHexane off the top, water out of the bottom, nothing to the drainRate from 3,926 kg + 5 days labour — Gravity separator, boiling tank and interlocks | 25 m³ | 1set | — | estimated | 1,583,088 |
| Vent gas absorption (mineral oil scrubber)The difference between 1 and 3 kg of hexane lost per tonneRate from 10,100 kg + 8 days labour — Absorber, desorber, circulation and chiller | 240 kg/day at risk | 1system | — | estimated | 4,060,000 |
| Crude oil tank, MSA day of extracted oil before it goes to refiningRate from 3,724 kg + 5 days labour — Tank with heating coil | 40 m³3.1 t each | 2tank | 6.2t | estimated | 3,003,914 |
Rising-film evaporator, MS
Two stages take the miscella from about 25% to 90% oil
Rate from 12,935 kg + 6 days labour — Tube bundle, shell and separator, per m²- Size
- 136.2 m² · 12.9 t each
- No.
- 2stage
- Total weight
- 25.9 t
- Rate(estimated)
- Amount
- ₨ 10,378,060
Final stripping column, MS
Steam strips the last hexane out of the oil
Rate from 2,929 kg + 8 days labour — Packed or disc-and-doughnut column with sparge- Size
- 1.65 m³/h oil · 2.1 t each
- No.
- 1column
- Total weight
- 2.1 t
- Rate(estimated)
- Amount
- ₨ 1,191,692
Solvent condensers
Condense the hexane vapour from DT, evaporators and stripper
Rate from 25,208 kg + 4 days labour — Shell and tube condenser, per m²- Size
- 296.6 m²
- No.
- 3unit
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 30,279,999
Solvent-water separator and boiling tank
Hexane off the top, water out of the bottom, nothing to the drain
Rate from 3,926 kg + 5 days labour — Gravity separator, boiling tank and interlocks- Size
- 25 m³
- No.
- 1set
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 1,583,088
Vent gas absorption (mineral oil scrubber)
The difference between 1 and 3 kg of hexane lost per tonne
Rate from 10,100 kg + 8 days labour — Absorber, desorber, circulation and chiller- Size
- 240 kg/day at risk
- No.
- 1system
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 4,060,000
Crude oil tank, MS
A day of extracted oil before it goes to refining
Rate from 3,724 kg + 5 days labour — Tank with heating coil- Size
- 40 m³ · 3.1 t each
- No.
- 2tank
- Total weight
- 6.2 t
- Rate(estimated)
- Amount
- ₨ 3,003,914
Safety, pumps and pipe
| Material | Size | No. | Total weight | Rate | Amount |
|---|---|---|---|---|---|
| Nitrogen blanketing and gas detectionHexane is flammable at 1.1% in air — this is not optionalRate from 1,800 kg + 10 days labour — Generator, distribution, detectors and interlocks | plant-wide | 1system | — | estimated | 745,000 |
| Miscella and solvent pumps, seallessCanned or magnetic drive — a leaking seal on hexane is a fireRate from 820 kg + 1 day labour — Sealless pump set, flameproof motor | 15.1 m³/h | 6pump | — | estimated | 1,982,298 |
| MS pipe, seamlessSized at 1.5 m/s; length is a starting allowance, not a routeRate from 13 kg + 0.1 days labour — MS at NB 80 mm, welded and tested for solvent duty | NB 80 mm0.01 t each | 700m | 6.2t | estimated | 3,871,000 |
| Valves, flameproof dutyIsolation and control across extraction and recoveryRate from 43 kg + 0.25 days labour — Valve, NB 80 mm | NB 80 mm | 70valve | — | estimated | 1,253,350 |
Nitrogen blanketing and gas detection
Hexane is flammable at 1.1% in air — this is not optional
Rate from 1,800 kg + 10 days labour — Generator, distribution, detectors and interlocks- Size
- plant-wide
- No.
- 1system
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 745,000
Miscella and solvent pumps, sealless
Canned or magnetic drive — a leaking seal on hexane is a fire
Rate from 820 kg + 1 day labour — Sealless pump set, flameproof motor- Size
- 15.1 m³/h
- No.
- 6pump
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 1,982,298
MS pipe, seamless
Sized at 1.5 m/s; length is a starting allowance, not a route
Rate from 13 kg + 0.1 days labour — MS at NB 80 mm, welded and tested for solvent duty- Size
- NB 80 mm · 0.01 t each
- No.
- 700m
- Total weight
- 6.2 t
- Rate(estimated)
- Amount
- ₨ 3,871,000
Valves, flameproof duty
Isolation and control across extraction and recovery
Rate from 43 kg + 0.25 days labour — Valve, NB 80 mm- Size
- NB 80 mm
- No.
- 70valve
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 1,253,350
Material
₨ 158,365,836
161.0 t of steel to fabricate
Labour
₨ 733,750
294 days at ₨ 2,500 a day
Quotation total
₨ 159,099,586PKR
23 of 23 lines priced
161.04 t is fabricated steel only. 14 bought-in lines — pumps, machines, proprietary units — are priced but carry no steel weight of ours, and show a dash in the weight column.