Water treatment & RO plant

Enter the treated water you need and what is in the feed. The list below is what that implies — sand and carbon filters, dosing, membranes and vessels, the high pressure pump, and storage — with a rate column you fill in yourself.

How this works →

Your figures

Treated water out, not raw water in.

Sized on running hours; the balance is backwash and CIP.

Brackish water up to about 10,000. Above that the pressures and the membranes change.

Permeate as a share of feed. The rest leaves as reject.

Material take-off

What to buy, at what size, and how many — worked out from the figures above.

Rates

Every line is estimated from those two figures: its steel — or steel-equivalent — mass at the steel rate, stainless at 3.2×, plus its install days at the labour rate. There is no price feed behind this, so the two anchors are seeded from typical Pakistan figures as of September 2026 and are yours to correct. Type over any individual rate and yours is used instead.

Pre-treatment

  • Raw water tank, MS epoxy lined

    Two hours of feed, so the plant rides out a supply interruption

    Rate from 4,718 kg + 5 days labour — Tank with lining, level and overflow
    Size
    75 m³ · 3.9 t each
    No.
    1tank
    Total weight
    3.9 t
    Rate(estimated)
    Amount
    ₨ 1,899,829
  • Multigrade sand filter, FRP

    Turbidity and suspended solids out before the membranes

    Rate from 1,136 kg + 3 days labour — FRP vessel, media, valves and piping
    Size
    35.7 m³/h
    No.
    2vessel
    Total weight
    —
    Rate(estimated)
    Amount
    ₨ 923,572
  • Activated carbon filter, FRP

    Chlorine out — it destroys a polyamide membrane in hours

    Rate from 1,237 kg + 3 days labour — FRP vessel, carbon, valves and piping
    Size
    35.7 m³/h
    No.
    2vessel
    Total weight
    —
    Rate(estimated)
    Amount
    ₨ 1,004,714
  • Antiscalant and SMBS dosing skids

    Scale control and residual chlorine quench

    Rate from 260 kg + 2 days labour — Tank, metering pump, and calibration column
    Size
    0.007 m³/h
    No.
    2skid
    Total weight
    —
    Rate(estimated)
    Amount
    ₨ 218,000
  • 5 micron cartridge filter housing

    The last guard before the high-pressure pump

    Rate from 501 kg stainless-equivalent + 1 day labour — SS housing and cartridges
    Size
    35.7 m³/h
    No.
    1housing
    Total weight
    —
    Rate(estimated)
    Amount
    ₨ 644,329

Reverse osmosis

  • High pressure pump, SS 316

    Duty and standby — the plant stops without it

    Rate from 1,589 kg stainless-equivalent + 3 days labour — Multistage pump, motor, VFD and baseplate
    Size
    35.7 m³/h at 15 bar
    No.
    2pump
    Total weight
    —
    Rate(estimated)
    Amount
    ₨ 4,083,206
  • Membrane pressure vessel, FRP, 6-element

    34 elements at 37 m² each, six to a vessel

    Rate from 260 kg + 1.5 days labour — FRP vessel, end caps and interconnectors
    Size
    8040, 6 vessels
    No.
    6vessel
    Total weight
    —
    Rate(estimated)
    Amount
    ₨ 646,500
  • RO membrane element, 8040

    20 litres per m² per hour at 1,500 mg/l feed

    Rate from 120 kg + 0.1 days labour — Spiral-wound polyamide element
    Size
    1,250 m² total
    No.
    34element
    Total weight
    —
    Rate(estimated)
    Amount
    ₨ 1,640,500
  • RO skid, frame, instruments and panel

    Flow, pressure and conductivity on feed, permeate and reject

    Rate from 2,400 kg stainless-equivalent + 10 days labour — SS frame, high-pressure piping, instruments and PLC
    Size
    25 m³/h permeate
    No.
    1skid
    Total weight
    —
    Rate(estimated)
    Amount
    ₨ 3,097,000
  • Membrane CIP system

    Acid and alkali cleaning when the pressure drop rises

    Rate from 840 kg stainless-equivalent + 4 days labour — Tank, heater, pump, filter and hoses
    Size
    4 m³
    No.
    1system
    Total weight
    —
    Rate(estimated)
    Amount
    ₨ 1,085,200

Post-treatment & storage

  • UV steriliser

    Final disinfection on the permeate

    Rate from 240 kg stainless-equivalent + 1 day labour — SS chamber, lamps and controller
    Size
    25 m³/h
    No.
    1unit
    Total weight
    —
    Rate(estimated)
    Amount
    ₨ 309,700
  • Remineralisation and pH correction

    RO permeate is aggressive and flat — it needs hardness back for drinking

    Rate from 650 kg + 3 days labour — Calcite contactor, dosing and mixer
    Size
    25 m³/h
    No.
    1set
    Total weight
    —
    Rate(estimated)
    Amount
    ₨ 267,500
  • Treated water tank, MS lined

    8 hours of permeate, over 2 tanks

    Rate from 5,716 kg + 5 days labour — Tank with food-grade lining, level and vent filter
    Size
    100 m³ · 4.8 t each
    No.
    2tank
    Total weight
    9.5 t
    Rate(estimated)
    Amount
    ₨ 4,597,672
  • Distribution pump set with hydro-pneumatic vessel

    Peak draw is above the average production rate

    Rate from 1,098 kg stainless-equivalent + 2 days labour — Pump, motor, vessel and controls
    Size
    37.5 m³/h
    No.
    2pump
    Total weight
    —
    Rate(estimated)
    Amount
    ₨ 2,820,880
  • Reject handling and discharge line

    30% of feed leaves as reject — it has to go somewhere legal

    Rate from 601 kg + 3 days labour — Sump, pump, flow meter and line
    Size
    10.7 m³/h
    No.
    1set
    Total weight
    —
    Rate(estimated)
    Amount
    ₨ 248,071

Material

₨ 23,298,171

13.5 t of steel to fabricate

Labour

₨ 188,500

75 days at ₨ 2,500 a day

Quotation total

₨ 23,486,673PKR

15 of 15 lines priced

13.46 t is fabricated steel only. 13 bought-in lines — pumps, machines, proprietary units — are priced but carry no steel weight of ours, and show a dash in the weight column.

Questions

How is the membrane count worked out?
From flux — how many litres each square metre of membrane passes per hour. Brackish water runs around twenty, falling as the feed gets saltier, because a dirtier feed has to be pushed harder and fouls faster. The area divided by thirty-seven gives the number of 8040 elements, six to a pressure vessel.
Why does recovery matter?
It sets how much raw water you have to pump and treat for a given output, and how much reject you have to dispose of. At seventy percent recovery, every cubic metre of permeate needs one point four of feed — and the remaining zero point four leaves as concentrate that has to go somewhere legal.
Why is the carbon filter essential?
Because chlorine destroys a polyamide membrane in hours, not months. The carbon filter and the bisulphite dosing are the two things standing between a chlorinated supply and a very expensive replacement.
What is not included?
The bore well or raw supply, civil work and the plant room, the electrical supply, effluent or brine disposal beyond the discharge line, and any specialist post-treatment such as ozonation or bottling.